Metrowest was engaged by Fulton Hogan to complete the following:
• Assemble 25m of Tower on site
• Remove 25m Top Section of Tower and replace with new section
• Reinstate Existing Microwave Dishes
• Sand Blast Bottom 10m of Tower
• Paint 10m of tower according to clients specifications.
Dispose of 25m TowerClient: Fulton Hogan
Timeframe: 2 weeks



